January 25 2010

Public Hearing Feb 2010

February 23 2010

March 19 2010

Sewer Connection List

       Public Meeting February 23rd, 2010 
                                   Sagle Elementary School
                             550 Sagle Road, Sagle at 7:00pm 

Public Hearing to Consider Judicial 
             Confirmation
                                                           
      Minutes February 18 2010


Panel Members

Board members: Chairman Jim Haynes, Vice-Chair Bill Jones, Directors Gary Wescott,Brent Sleep and Bruce Vogelsinger. Maintenance Supervisor Doug Bopp, DEQ John Tndall, Engineer Paul Klatt and Attorney Ted Diehl.


Jim Haynes opened the meeting at 7:00pm. With 61 in attendance.
Sign up sheet attached to original minutes.

Gary Wescott gave an informative history of the District.


Jim Haynes reviewed the past 6 years relating to the District’s moratorium.


Jim Haynes presented the current 3 options available to the District.

1. Proceed with Judicial Confirmation in order to add 40 -60 ERU’s by fully utilizing the existing wastewater application site at a cost of approximately $1,200.000 or $17.00 per month per user.

2. Work with Bonner County and Sagle Valley Water & Sewer to form an Urban Renewal District in an effort to fund a jointly owned expanded system. Due to the number of authorizations by various political jurisdictions this could take as long as five (5) years with no guarantee.


3. 
Assuming a positive outcome of the study to determine the level of prosperous in the Pend Oreille River, pursue an MBR treatment system. This could costs as much as $2.8 million or $40.00 per month per user, and several years to accomplish

Jacquie Albright read letters from Richard Wingerson, Colleen Russell, Jeanne Jackson-Heim, Ann Bacon Wagstaff and Mr. Overholser.

The floor was then opened for questions from those in attendance.


The meeting adjourned at 8:30pm